NOVATEK has commenced the third LNG train production at its joint venture Yamal LNG. The total nameplate capacity of all three LNG trains is 16.5 mmtpa, or 5.5 mmtpa per LNG train.

“We have successfully launched all three LNG trains at our flagship Yamal LNG project according to our revised early launch schedule clearly confirming the uniqueness of Yamal LNG in the global LNG industry,” noted NOVATEK’s Chairman of Management Board Leonid Mikhelson, “We have not only launched all three technological trains on budget, but have launched the third LNG train more than one year ahead of the planned original schedule. This fact is unprecedented for the industry plagued by massive cost overruns and project delays.